Shinhan Engineering & Construction Co. v. State of Libya
Case summary
At a glance
- Parties
- Shinhan Engineering & Construction Co. (Korea) v. State of Libya
- Forum and rules
- Not stated in the published document
- Treaty
- Libya–Korea bilateral investment treaty
- Sector
- Construction; housing and infrastructure
- Outcome
- Final award of 18 April 2023 rejected all of the claimant's claims and ordered it to pay Libya's costs, according to Libya's press release.
- Amount
- Claimed: LYD 660,560,359.00 plus interest and legal costs. Awarded to the claimant: nothing. Costs ordered against the claimant: USD 194,931,10.00 [figure as printed] for arbitration costs and GBP 1,267,083.00 for legal fees and expert and witness costs, each payable within 60 days, then bearing interest at 5% a year, compounded twice.
The dispute
Shinhan Engineering & Construction Co., a Korean construction company, brought an investment treaty claim against the State of Libya under the Libya–Korea bilateral investment treaty. The claim concerned four projects for residential buildings and infrastructure in Zliten, Tripoli and Zawiya. Shinhan alleged that the Libyan bodies it had contracted with breached their obligations. These were the Authority for the Development and Improvement of Administrative Centres and the Authority for the Implementation of Housing and Utilities Projects. Shinhan claimed LYD 660,560,359.00 in compensation, with interest until full payment, and all its legal costs. The only published document is a short press release in Arabic from Libya's State Litigation Department. It does not give Libya's defences, the tribunal's reasoning, the forum or the arbitrators.
Key holdings
- In a final award dated 18 April 2023, the tribunal rejected all of the claimant's claims, as reported by Libya's State Litigation Department. Press release, p. 1
- The claimant must pay Libya USD 194,931,10.00 (figure as printed) for the arbitration costs Libya incurred, within 60 days of notification of the award. After that, the amount bears interest at 5% a year, compounded twice, until paid in full. Press release, p. 1, item 1
- The claimant must also pay Libya GBP 1,267,083.00 for legal fees and expert and witness costs, within 60 days of notification of the award, on the same interest terms. Press release, p. 1, item 2
Procedural history
Tribunal, counsel and experts
- For the respondent
- State Litigation Department of Libya (Foreign Disputes Section)
Run a conflict check on these names →
Keywords
- Shinhan
- Libya
- Libya–Korea BIT
- construction contracts
- housing projects
- infrastructure
- Zliten
- Tripoli
- Zawiya
- Housing and Utilities Projects authority
- Administrative Centres authority
- costs award
- claims dismissed
- State Litigation Department
Summary generated with AI from the published documents — refer to the award for the authoritative text.