Pawlowski AG vs. Czech republic
Case summary
At a glance
- Parties
- Pawlowski AG (Switzerland) and Projekt Sever s.r.o. (Czech Republic) v. Czech Republic
- Case no.
- ICSID Case No. ARB/17/11 (and Annulment Proceeding)
- Forum and rules
- ICSID Convention arbitration; ICSID Arbitration Rules 2006; place of proceeding Paris
- Treaty
- Czech and Slovak Federal Republic–Switzerland BIT, signed 5 October 1990, in force 7 August 1991
- Tribunal
- Prof. Juan Fernández-Armesto (President), Mr. John Beechey, Prof. Vaughan Lowe
- Committee
- Dr. Jacomijn J. van Haersolte-van Hof (President), Ms. Yoshimi Ohara, Mr. David A. Pawlak
- Sector
- Real estate development; zoning
- Outcome
- Award of 1 November 2021: jurisdiction upheld; the Czech Republic breached Article 4 of the BIT through the Benice mayor's payment demands; a declaration was granted, no compensation was awarded and all other claims were dismissed. The claimants' application for partial annulment was rejected on 7 March 2025.
- Amount
- Claimed: CZK 5,266,622,342, including pre-award interest as of 31 July 2020. Awarded: nothing. Arbitration costs of USD 617,413.86 were shared equally, and each party bore its own legal fees. In the annulment, the applicants bore the costs of the proceeding (USD 375,994.52), and each party bore its own legal costs.
The dispute
Pawlowski AG, a Swiss company, owns Projekt Sever s.r.o. Between June 2007 and December 2008, Projekt Sever bought about 270,000 m2 of agricultural land in the Prague district of Benice to build a residential complex. It bought from private owners, from the City of Prague and from the Ministry of Defense, while zoning change Z 1294/07 was still pending. The Prague City Assembly approved the change on 26 March 2010, and the permitted density was raised in 2011. In June 2012, Benice and two neighbours sought judicial annulment of the change. The Prague Municipal Court annulled it on 26 April 2013, the Supreme Administrative Court confirmed the annulment on 26 February 2014, and on 14 April 2015 the City Assembly voted 51:0 not to re-procure it. The claimants alleged unreasonable and discriminatory measures and breach of fair and equitable treatment (Article 4), failure to grant necessary permits (Article 3(2)) and indirect expropriation (Article 6). The Czech Republic raised jurisdictional objections and argued that its authorities acted lawfully, made no specific representations and took no acquired rights, and that the damages claimed were speculative.
Key holdings
- The Tribunal unanimously dismissed all of the Czech Republic's jurisdictional objections. Award, dispositif ¶ 1
- The only breach found was the payment demands made to Projekt Sever on behalf of the Benice District by Mayor Topičová. These were demands for money in return for withdrawing the Benice Lawsuit and for the District's change of position on the density increase. They were unreasonable measures under Article 4(1) and fell short of fair and equitable treatment under Article 4(2). Award, pp. 151, 153
- The filing of the Annulment Request, the court annulment, the City Assembly's reasoned and unanimous decision not to re-procure, and Benice's opposition to re-procurement were not breaches. No discrimination was shown, because the claimants identified no comparator in a similar situation that received better treatment; Central Group's project in particular was not comparable. Award, pp. 112–125
- There was no legitimate expectation. The purchase contracts described the land as agricultural and contained no assurance that it would be rezoned. The officials' support was general and oral, and came from authorities without competence over the zoning change. Approval of the change remained open to judicial challenge. Award, pp. 138–141
- Article 3(2) does not cover zoning plan changes, which are rules of general application and not permits; in any event Czech law was followed. There was no indirect expropriation: the claimants acquired only rights over agricultural, forest and recreational land, and they still own it. Award, pp. 144–151
- Compensation was refused because the claimants showed no damage and no causal link between the wrongful payment demands and the losses claimed. As satisfaction, the Tribunal declared that Article 4 had been breached. Under the default rule in Article 9(2)(d) of the BIT, the costs of the proceeding were shared equally and each party bore its own legal fees. Award, pp. 155–160
- The Committee unanimously rejected all eight annulment grounds raised under Articles 52(1)(d) and (e). The Tribunal was not required to address every piece of evidence, including the Štěpánková evidence. By rejecting each claim individually, it implicitly rejected the argument that the measures should be assessed cumulatively. Its incorrect reference to a two-year limitation period was immaterial, because the decisive point was that the zoning change could be, and was, challenged in court. Decision on Annulment ¶¶ 161–163, 198, 300–303, 372
Procedural history
- 7 April 2017ICSID received the Request for Arbitration. It was registered on 3 May 2017.
- 6 November 2017The Tribunal was constituted.
- 13 February 2018Procedural Order No. 1 set out the procedural rules and timetable; the place of proceeding was Paris.
- 26–30 January 2020Hearing on jurisdiction, merits and quantum held in Paris.
- 16 June 2020Procedural Order No. 5 admitted Ms. Štěpánková's Facebook post as new evidence and allowed the Czech Republic to file her affidavit in reply.
- 1 November 2021Award: breach of Article 4 declared; no compensation awarded; all other claims dismissed.
- 26 February 2022The claimants applied for partial annulment. The application was registered on 9 March 2022, and the ad hoc Committee was constituted on 23 May 2022.
- 17 January 2024The annulment proceeding was suspended because the applicants had not paid the required advance, and the January 2024 hearing was cancelled. The proceeding resumed on 12 April 2024.
- 10 September 2024Hearing on partial annulment held in Prague.
- 7 March 2025Decision on Annulment: the application was rejected, and the applicants were ordered to bear the costs of the proceeding.
Tribunal, counsel and experts
- Decided by
- Juan Fernández-Armesto President — appointed by the parties jointly
- John Beechey Co-arbitrator — appointed by the claimant
- Vaughan Lowe Co-arbitrator — appointed by the respondent
- Jacomijn J. van Haersolte-van Hof Committee president — appointed by the institution
- Yoshimi Ohara Committee member — appointed by the institution
- David Pawlak Committee member — appointed by the institution
- For the claimant
- Homburger AG · Havlíček Law Offices / Havlíček Haman, advokátní kancelář s.r.o. · MACH LEGAL, advokátní kancelář s.r.o. · JUDr. Filip Černý, Ph.D., advokát
- For the respondent
- Dechert LLP · Wordstone Dispute Resolution AARPI · Ministry of Finance of the Czech Republic
- Experts
- Veronika Tomoszková (claimant) · Kai F. Schumacher (claimant) · Clark Fraser (claimant) · Stanislav Kadečka (respondent) · Fernando Cuñado Garcia-Bernalt (respondent) · Jiří Urban (respondent) · Martin Staněk (respondent)
Run a conflict check on these names →
Keywords
- Czech Republic–Switzerland BIT
- unreasonable measures
- fair and equitable treatment
- legitimate expectations
- indirect expropriation
- discrimination
- national treatment
- zoning plan change
- real estate development
- Prague
- Benice
- payment demands
- causation
- satisfaction
- declaratory relief
- annulment
- failure to state reasons
- right to be heard
Summary generated with AI from the published documents — refer to the award for the authoritative text.