Latam Hydro LLC and CH Mamacocha S.R.L. v. Republic of Peru
Case summary
At a glance
- Parties
- Latam Hydro LLC (United States) and CH Mamacocha S.R.L. (Peru) v. Republic of Peru
- Case no.
- ICSID Case No. ARB/19/28
- Forum and rules
- ICSID Convention; ICSID Arbitration Rules 2006, as modified by Chapter Ten, Section B of the TPA; place of proceeding Washington, D.C.
- Treaty
- United States–Peru Trade Promotion Agreement (signed 12 April 2006, in force 1 February 2009); also the RER Concession Contract of 18 February 2014
- Tribunal
- Prof. Dr. Albert Jan van den Berg (President), Prof. Dr. Guido Santiago Tawil, Prof. Raúl E. Vinuesa
- Sector
- Renewable energy; small hydroelectric plant
- Outcome
- Award of 20 December 2023: jurisdiction upheld except over the Upstream Projects. By majority, all treaty and contract claims were rejected. The RER Contract was declared terminated and the USD 5 million Performance Bond is to be returned. Tawil dissented in part on the merits.
- Amount
- Claimed: at least USD 45,620,000. Awarded: nothing, but Peru may not call the USD 5 million Performance Bond and must return it. Claimants bear the arbitration costs of USD 1,508,304.41 and must reimburse Peru USD 754,152.21, with 3% interest compounded annually. Each side bears its own legal costs (claimants had claimed USD 17,522,014.25–23,318,729.25; Peru USD 4,804,833.80).
The dispute
Latam Hydro LLC, a Delaware company, and its Peruvian subsidiary CH Mamacocha S.R.L. (CHM) developed the Mamacocha Project, a 20 MW run-of-the-river hydroelectric plant and transmission line near the Mamacocha Lagoon in Arequipa. CHM won Peru's Third RER Auction and signed the RER Contract with the Ministry of Energy and Mines (MINEM) on 18 February 2014. Under that contract, commercial operation had to start by 31 December 2018, and the termination date of 31 December 2036 could not be changed. MINEM granted two extensions (Addenda 1 and 2) for permitting delays attributed to the State. The project then faced several obstacles: a lawsuit by the Regional Government of Arequipa to annul its environmental permits, a criminal investigation, delays in the civil works authorisation, and an amparo judgment annulling the permits. In December 2018 MINEM started a domestic arbitration in Lima to annul Addenda 1 and 2 and refused a third extension. The claimants alleged breach of the RER Contract and Peruvian law, and breach of the TPA's fair and equitable treatment, expropriation and MFN provisions. Peru raised jurisdictional objections and argued that the contract's deadlines were mandatory and that it had acted as a contracting party, not as a sovereign.
Key holdings
- Jurisdiction was upheld over Latam Hydro's TPA claims, brought on its own behalf and on behalf of CHM, and over CHM's claims under the RER Contract. The exception: there is no jurisdiction ratione materiae over the claims concerning the Upstream Projects. Award ¶ 1412(A)–(B)
- Peru did not breach the RER Contract by rejecting the Third Extension Request. Neither the contract nor Peruvian law gives a right to extend the commercial operation start date or the termination date. An extension would have been inconsistent with the contract and with the binding RER Regulations. Starting the Lima Arbitration was a legitimate use of the contract's domestic arbitration clause. The majority rejected all of CHM's contract claims. Award ¶¶ 1203, 1213
- Where Peru acted within the contractual relationship rather than as a sovereign, and the matching contract claim fails, the TPA claim based on the same conduct fails as well. The Lima Arbitration and the denial of the extension were acts of a contracting party. Award ¶¶ 1193, 1202, 1216
- No breach of fair and equitable treatment (TPA Art. 10.5). The RGA Lawsuit, the criminal proceedings, the handling of the civil works authorisation, the Lima Arbitration and the denial of the extension were not arbitrary, discriminatory, lacking in transparency or in bad faith. They did not defeat reasonable expectations, whether taken one by one or together. The evidence does not support a concerted plan to destroy the project. Award ¶¶ 1221–1228
- No indirect expropriation (TPA Art. 10.7 and Annex 10-B). The measures did not interfere with reasonable investment-backed expectations, and the contractual measures could not be expropriatory. An adverse economic effect alone is not enough, so the Tribunal did not decide on economic impact. The MFN claim (Art. 10.4) also failed: there was no breach of Art. 3(2) of the Paraguay–Peru BIT, and with no breach of contract there was nothing an umbrella clause could protect. Award ¶¶ 1253–1259, 1270–1278
- Peru breached Clause 3 of the 2017 Confidentiality Agreement through the testimony of its witness Mr. Ampuero about the settlement talks. The breach was not material and did not end the agreement under Arts. 1428–1429 of the Peruvian Civil Code. The claimants' request to declare the agreement terminated was rejected. Award ¶¶ 1306–1317
- Costs: under Clause 11.7 of the RER Contract and the principle that costs follow the event, the claimants jointly bear the arbitration costs of USD 1,508,304.41 and reimburse Peru USD 754,152.21, with 3% interest compounded annually. Each side bears its own legal and other costs, because the claimants defeated all but one of Peru's jurisdictional objections and their claims were not frivolous. Award ¶¶ 1380–1390
- Dissent: Tawil found that Peru breached Clauses 1.4.26, 1.4.37 and 6.3 of the RER Contract and the fair and equitable treatment standard under Art. 10.5. In his view, refusing the third extension despite delays not attributable to the concessionaire, and disavowing Addenda 1 and 2, destroyed the contract's financial-economic balance. Dissenting Opinion ¶¶ 8–10
Procedural history
- 19 June 2017First notice of intent under TPA Art. 10.15. It was withdrawn on 17 April 2018 after the RGA Lawsuit was withdrawn.
- 30 August 2019ICSID receives the Request for Arbitration, supplemented by letter of 18 September 2019. ICSID registers it on 19 September 2019.
- 9 March 2020Tribunal constituted.
- 15 April 2020Procedural Order No. 1 rejects Peru's application to strike confidential information from the notice of intent and the Request for Arbitration.
- 13 May 2020Procedural Order No. 2 sets the procedural rules and timetable.
- 3 May 2021Procedural Order No. 4 decides disputed privilege claims: six Peruvian documents are ordered disclosed and the other claims are upheld.
- 19 November 2021The United States files a non-disputing party submission under TPA Art. 10.20(2).
- 7–18 March 2022Virtual hearing on jurisdiction, merits and quantum.
- 20 December 2023Award: claims rejected by majority. RER Contract declared terminated; Performance Bond to be returned. Tawil dissents in part.
Tribunal, counsel and experts
- Decided by
- Albert Jan van den Berg President — appointed by the parties jointly
- Guido Santiago Tawil Co-arbitrator — appointed by the claimant (dissented in part on the merits)
- Raúl E. Vinuesa Co-arbitrator — appointed by the respondent
- For the claimant
- Baker & Hostetler LLP
- For the respondent
- Comisión Especial del Ministerio de Economía y Finanzas · Arnold & Porter Kaye Scholer LLP · Garrigues
- For other participants
- U.S. Department of State, Office of the Legal Adviser
- Experts
- María Teresa Quiñones Alayza (claimant) · Eduardo Benavides Torres (claimant) · John McTyre (claimant) · Santiago Dellepiane (claimant) · Andrea Cardani (claimant) · Michael Whalen (claimant) · Christoph Schreuer (claimant) · Claudio Lava Cavassa (respondent) · Carlos Javier Monteza Palacios (respondent) · Matthew D. Shopp (respondent) · Kiran Sequeira (respondent)
Run a conflict check on these names →
Keywords
- Mamacocha
- hydroelectric
- renewable energy
- RER Contract
- United States–Peru Trade Promotion Agreement
- fair and equitable treatment
- indirect expropriation
- most-favoured-nation clause
- umbrella clause
- contract vs. treaty claims
- sovereign vs. commercial acts
- extension of commercial operation date
- performance bond
- Lima Arbitration
- environmental permits
- confidentiality agreement
- non-disputing party submission
- Arequipa
Summary generated with AI from the published documents — refer to the award for the authoritative text.