POL India Projects Limited and other v. Aurelia Reederei Eugen Friederich GmbH Schiffahrtsgesellschaft & Company KG and other
Tribunal, counsel and experts
- Decided by
- R.D. Dhanuka Judge, High Court of Bombay — appointed by a court award
- Ben Horn President — chosen by the co-arbitrators (chairman of the arbitral tribunal between Aurelia and POL India Projects (as described in the judgment)) award
- Alan Oakley Co-arbitrator — appointed by the claimant (nominee of Aurelia (the claimant in the arbitration)) award
- Ashwin Shankar Co-arbitrator — appointed by the respondent (nominee of POL India Projects Limited) award
- Edward Mocatta President — chosen by the co-arbitrators (chairman of the arbitral tribunal in the separate arbitration between Aurelia and D.B. Shipping LLC) award
- For the claimant
- Bose & Mitra
- For the respondent
- Motiwala & Co.
Run a conflict check on these names →
Read with AI from the published documents; each name links to the person’s record. A full case summary follows when it is written.
Case ID
High Court of Bombay, No. Arbitration Petition No. 76 and 12 of 2012
Country
Claimant
POL India Projects Limited and other
Respondent
Aurelia Reederei Eugen Friederich GmbH Schiffahrtsgesellschaft & Company KG and other
Documents
Judgment of the High Court of Bombay
8 April 2015
Judgment of the High Court of Bombay
(416.25 KB)
Section
Court: India, High Court of Bombay
Date of decision: 08 April 2015
Case number: Arbitration Petition No. 76 and 12 of 2012
New York Convention provisions: V | V(2) | V(2)(b)
Source: New York Convention case law case database.